Gumbo, Rejaf Payam · Juba County · South Sudan

Clean water. Stronger communities. A healthier future.

Our Infrastructure

Gumbo Water Supply Project

Infrastructure designed for community needs

Initiated in 2018 to help reduce cholera and other waterborne diseases, the Gumbo Water Supply Project was officially commissioned and handed over by the ICRC to the Central Equatoria State Ministry of Housing, Lands and Public Utilities on 6 August 2025.

Designed treatment capacity of 10,000 m³ per day, with a planned 20-hour daily operating design.

Two elevated tanks at Sudken, each with a capacity of 500 m³, around 3.5 km from the pumping station.

Approximately 36 km of pipelines, 27 kiosks referenced in current operations, and two tanker filling stations.